What has to happen before this can start? · Scope Economics
scopeeconomics
What has to happen before this can start?
1 / 4
1. Project brief
The delivery scheme
Two work packages must be ready for one handover. You are connecting their activities and checking which sequence controls completion.
Water main and independent kiosk · WMK-1
Planning · WMK-1
What has to happen before this can start?
The water main and kiosk must both be ready for handover. Build the relationships that make that possible.
Opening saved workspace
Water-main and kiosk project · BL-1
Supplied Scope teaching baseline, version 1. Scenario approval supplied for learning; independent technical review pending. Scope WMK-1. Independent kiosk package completion includes installation, connection, testing and acceptance.
Calendar: Monday to Friday, no holidays. Day 0 is Wed 14 Oct 2026 start; day 8 is Fri 23 Oct close. Durations use whole working days. Only finish-to-start, zero lag and zero-duration milestones are supported.
CA-WM maps all ten bay budgets to activity P. Excavation, final system testing and kiosk costs are outside this control account.
Show a short worked example
If inspection must finish before covering a joint, link inspection to covering. Two independent deliveries do not need a dependency just because one appears first in a list.
Terms for this task
A predecessor is work that must finish before another activity can start. A milestone marks a required event, here handover, and has no duration.