D-08 · Site diary · Fri 23 Oct closeInstallation diary
At Friday close, bays 01 to 07 are physically installed. Bays 08 to 10 have not started. Local inspections are recorded separately. Signed site diary, revision 1.
Authored teaching record · WMK-1 · retained sourceI-01 · Inspection register · Wed 21 Oct closeBay 01 inspection
Local installation inspection accepted. Integrated main testing is still separate.
Authored teaching record · WMK-1 · retained sourceI-02 · Inspection register · Wed 21 Oct closeBay 02 inspection
Local installation inspection accepted. Integrated main testing is still separate.
Authored teaching record · WMK-1 · retained sourceI-03 · Inspection register · Wed 21 Oct closeBay 03 inspection
Local installation inspection accepted. Integrated main testing is still separate.
Authored teaching record · WMK-1 · retained sourceI-04 · Inspection register · Fri 23 Oct closeBay 04 inspection
Local installation inspection accepted. Integrated main testing is still separate.
Authored teaching record · WMK-1 · retained sourceI-05 · Inspection register · Fri 23 Oct closeBay 05 inspection
Local installation inspection accepted. Integrated main testing is still separate.
Authored teaching record · WMK-1 · retained sourceI-06 · Inspection register · Fri 23 Oct closeBay 06 inspection
Local inspection failed: joint defect. Rectification and repeat inspection required.
Authored teaching record · WMK-1 · retained sourceI-07 · Inspection register · Fri 23 Oct closeBay 07 inspection
Installed bay awaiting inspection. No acceptance certificate has been issued.
Authored teaching record · WMK-1 · retained sourceACT-P · Verified actuals · Fri 23 Oct closePipe crew daily reports
Installation started at boundary 5. Work remains at the cut-off. No actual finish is substantiated.
Authored teaching record · WMK-1 · retained sourceACT-P-ALT · Transfer actuals · Fri 23 Oct closeTransfer scenario: early installation start
Alternative teaching record, not an additional original actual: installation began at boundary 4 under a partial trench release. This replaces ACT-P for the transfer test. The full-trench predecessor did not finish until boundary 5. Preserve the actual and decide how to treat remaining logic.
Authored teaching record · WMK-1 · retained sourceF-P · Forecast basis · Fri 23 Oct closeRemaining installation assessment
Foreman and inspector allow two further full working days for three uninstalled bays, rectification and outstanding inspections. Crew and inspector are available Monday and Tuesday. This is an explicit forecast, not a percentage conversion.
Authored teaching record · WMK-1 · retained sourceBUD-01 · Budget baseline · Wed 14 Oct startCA-WM approved teaching budget
Ten equal-budget installation bays, £10,000 each. Local acceptance earns 100% of a bay; otherwise 0%. Six accepted bays planned by boundary 8. Final system testing, excavation and kiosk costs are outside this £100,000 account.
Authored teaching record · WMK-1 · retained sourceAC-08 · Cost record · Fri 23 Oct closeAccrued cost ledger, CA-WM
£70,000 incurred to the same cut-off for CA-WM, including accruals. This is not a cash-payments total.
Authored teaching record · WMK-1 · retained sourceIF-02 · Scope interfaceThe complete trench is handed over to the installation crew in this single-workface model.
IF-03 · Scope interfaceThe integrated main test requires all ten installed bays to pass local inspection.