A paid day of labour and plant delivers a measured length of main. You are pricing that contribution, then testing how a changed output affects the estimate.
120 m main · labour and plant
Unit rates · Training fixture
A paid day produces 18 metres
Calculate the labour and plant contribution, then test a different output and update the estimate.
Terms for this task
Productivity is the accepted output over a stated time. A unit rate expresses cost for one measured unit, here one metre.