Build a direct unit rate

1. Project brief
The installation work
The crew and machines are paid for their time. You are connecting that cost to the amount of finished work they produce.
Pipe installation · direct rateFind the permanent material
Select the permanent material in this pipe-laying operation.
Project details
- Project
- Water-main installation
- View
- Paid resources and accepted pipe
See the work in contextSite photograph · inspect the components
Separate what remains in the ground from the resources paid to install it.

Select a marker to connect the physical work to the estimate.
Image reference
Tomas Castelazo · CC BY-SA 3.0 · resized; numbered markers added.
Source: https://commons.wikimedia.org/wiki/File:114_inch_pipe_installation.jpg
Licence: https://creativecommons.org/licenses/by-sa/3.0/
On site
Connect the resources to the output

Illustrative scene. Use the lesson figures and records for measurements.
Finished main