The installed scope
A quotation covers supplied material. You are tracing delivery, losses and installation so the final rate covers the work actually required.
Material supply and installationMeasure permanent pipe
The drawing shows a 100 m main, a 20 m permanent tie-in and a 15 m temporary bypass hose. Select the permanent pipe to purchase.
Project details
- Project
- Water-main installation
- View
- Drawing and supplier quotation
See the work in contextSite photograph · inspect the components
The purchased length, delivered material and accepted installed quantity do not always match.

Select a marker to connect the physical work to the estimate.
Image reference
Tomas Castelazo · CC BY-SA 3.0 · resized; numbered markers added.
Source: https://commons.wikimedia.org/wiki/File:114_inch_pipe_installation.jpg
Licence: https://creativecommons.org/licenses/by-sa/3.0/
From delivered material to installed work

Illustrative scene. Use the lesson figures and records for measurements.
Which pipe remains in the finished asset?
Select the permanent segments. The dashed hose serves construction and is removed later.