An activity has been delayed. You are tracing the event through the programme before deciding whether handover is affected.
Water main and kiosk · delay reviewA supplier notice says the kiosk delivery will slip. Read the notice and the approved programme before changing the programme.
The physical workface is the starting point. Identify the location and the scope affected before judging progress or a delay.
Scope Economics · original explanatory diagram.
Illustrative scene. Use the lesson figures and records for measurements.
Working days from the same start. Drag the delivery finish or use the day buttons. The two paths can progress in parallel.