It is Friday. Where do we finish now?
1 / 4
1. Project brief
The reporting position
The original programme is the comparison point. You are using actual dates and remaining-work evidence to forecast the finish without rewriting that baseline.
Water main and independent kiosk · WMK-1
Project controls · WMK-1
It is Friday. Where do we finish now?
Use the same project records to separate completed work from the work still to come, then issue a supported forecast.
Opening saved workspace
Water-main and kiosk project · BL-1
Supplied Scope teaching baseline, version 1. Scenario approval supplied for learning; independent technical review pending. Scope WMK-1. Independent kiosk package completion includes installation, connection, testing and acceptance.
Calendar: Monday to Friday, no holidays. Day 0 is Wed 14 Oct 2026 start; day 8 is Fri 23 Oct close. Durations use whole working days. Only finish-to-start, zero lag and zero-duration milestones are supported.
CA-WM maps all ten bay budgets to activity P. Excavation, final system testing and kiosk costs are outside this control account.
Show a short worked example
An activity started before Friday and needs two more working days. Record its actual start and two days of remaining work. The remaining work starts after the Friday cut-off, once unfinished predecessors allow it. Do not convert installed percentage into duration.
Terms for this task
An actual date records an event supported by evidence. Remaining duration is a forecast of the work and availability still needed after the cut-off.