MERIDIAN HOUSE · FICTIONAL PROJECT

Confirm the completion position

40 min · 1 of 6 scenesProgress kept on this device
Completed office reception and collaboration space with oak finishes and navy seating
MERIDIAN HOUSE · FICTIONAL PROJECTClose the accountPractical completion was certified on 31 March 2028, but commercial closure still depends on defects, records and final testing.
01Practical completion certificate PC-0102Defects schedule D-0403Handover register H-09
Project record in view
ProgrammeOccupation achieved on 31 March 2028; defects and records remain controlled close-out actions.

Key evidence

Evidence to inspect
Project basis

Meridian House · 7,800 m²

Generated project illustration. Use the lesson records for quantities and decisions.
Your task

Separate occupation readiness, outstanding obligations and commercial closure.

Inspect one evidence item to continue.

Project records Cost plan · Changes · Risk · Programme
Cost plan£18.50m affordability limit established
Change registerCR-000 · baseline assumptions recorded
Risk allowances£1.35m initial project allowance
ProgrammeOccupation target · 31 March 2028