MERIDIAN HOUSE · FICTIONAL PROJECT

Assess the valuation

45 min · 1 of 6 scenesProgress kept on this device
Part-completed office partitions and exposed ceiling services at Meridian House
MERIDIAN HOUSE · FICTIONAL PROJECTControl cost on siteApplication 06 claims £5.82m at the 31 January 2028 data date. Only evidenced work enters the certificate.
01Measured work · £4.92m02Supported off-site materials · £0.36m03Preliminaries and design · £0.22m
Project record in view
Cost planInterim certificate 06 · £5.50m cumulative, £0.32m below the application.

Key evidence

Evidence to inspect
Project basis

Meridian House · 7,800 m²

Generated project illustration. Use the lesson records for quantities and decisions.
Your task

Build the certificate from evidenced progress rather than the contractor’s expenditure.

Inspect one evidence item to continue.

Project records Cost plan · Changes · Risk · Programme
Cost plan£18.50m affordability limit established
Change registerCR-000 · baseline assumptions recorded
Risk allowances£1.35m initial project allowance
ProgrammeOccupation target · 31 March 2028