RATE BUILD-UPS PRACTICE LAB
Price a cubic metre of concrete
Turn material, crew and pump costs into one transparent concrete rate.
On site
Separate the measured work

Illustrative scene. Use the lesson figures and records for measurements.
THE SCENARIO · GBP
Prepare a rate for 450 m³ of concrete. Material: 91.50 per m³, additional waste: 3%. Labour crew: 1,420 per day producing 72 m³ per day. Pump: 780 per day producing 180 m³ per day. Excludes reinforcement, formwork, overheads and profit.
Build your answer
Enter your results to two decimal places. Use full precision between calculation steps.