Find six errors hiding in a small construction estimate.

Illustrative scene. Use the lesson figures and records for measurements.
There are six issue types across this supply-and-install estimate. Two rows refer to the same duplicate. Classify each row; leave a sound row as “No issue”.
| Item | Description | Quantity basis | Rate | Total | Your review |
|---|---|---|---|---|---|
| 1.01 | Bulk excavation | 1,200 m³ | 5.50 | 6,600 | |
| 1.02 | Bulk excavation repeated | 1,200 m³ | 5.50 | 6,600 | |
| 1.03 | Concrete to slab | 450 m² | 117.50 per m³ | 52,875 | |
| 1.04 | Blockwork | 500 m² | Labour 15; material 0 | 7,500 | |
| 1.05 | Manual trench excavation | 800 m³ per hour | Crew 101 per hour | 0.13 per m³ | |
| 1.06 | Concrete material | 100 m³ | 91.50 × 3% waste | 274.50 | |
| 1.07 | Formwork | 100 m² | 32.00 | 320 | |
| 1.08 | Lean concrete blinding | 20 m³ | 105.00 | 2,100 |