Build the crew rate
Balance a four-person crew against achievable hourly output.
On site
Connect the resources to the output

Illustrative scene. Use the lesson figures and records for measurements.
THE SCENARIO · GBP
A crew has three operatives at 23 per hour each and one supervisor at 32 per hour. It produces 8 m³ per hour over an 8-hour working day. All hourly rates are fully loaded for this example.
Build your answer
Enter your results to two decimal places. Use full precision between calculation steps.