RISK & CONTINGENCY PRACTICE LAB
Price the uncertainty
Separate the base estimate from probability-weighted cost impacts.
On site
Locate the uncertain scope

Illustrative scene. Use the lesson figures and records for measurements.
THE SCENARIO · GBP
The base estimate is 100,000. Risk A has a 25% probability of an additional 20,000 cost. Risk B has a 10% probability of an additional 50,000 cost. Impacts do not overlap and neither is already included in the base.
Build your answer
Enter your results to two decimal places. Use full precision between calculation steps.
Members can save a draft and resume later.
Saving is available to site members. You can use the tools and export your calculations without saving an account record