Earthworks Calculator
Reconcile bank excavation, loose spoil, reuse and truck movements.
Material assumptions
Bank excavation1,200m³ in situ
Reused on site360 m³
Exported bank volume840 m³
After 25% swell1,050 m³Loose material for transport
59truck movements at 18 m³ each
Calculation method and assumptions
Export bank = Excavation × (1 − Reuse ÷ 100); Loose export = Export bank × (1 + Swell ÷ 100); Trips = ceiling(Loose export ÷ Capacity)Volumes use a stated bank-to-loose swell addition. Reuse is a percentage of bank excavation. No compaction, density or import balance is inferred.
Currency changes labels only. No exchange conversion is applied