Haul Cycle Calculator
Model truck cycles, production and indicative fleet size.
Trucks required4
12
10
4
2
3
Loaded travel12 minEmpty return10 minLoading4 minDumping2 minDelay3 min
0 minOne cycle: 31 minutes31 min
Cycle time (min)31
Cycles per hour1.94
Truck output (m³ per hour)34.84
Calculation method and assumptions
Cycle = Loaded travel + Empty travel + Loading + Dumping + Delay; Trucks = ceiling(Excavator output ÷ Truck output)Assumes consistent volume basis and cycle conditions. Fleet size is indicative; check queues, access and loading constraints.