Rate Build-Up Calculator
Combine labour, material and plant into a unit rate.
Resources per measured unit
| Resource | Cost per m³ |
|---|---|
| Labour | |
| Material | |
| Plant | |
| Subcontract | |
| Other |
Labour18.5Material92Plant7Subcontract0Other0
Unit rate per m³£117.50
Total estimated cost£11,750.00
Calculation method and assumptions
Unit rate = Labour + Material + Plant + Subcontract + Other; Total = Quantity × Unit rateAll components must use the same measured unit. No overhead, profit or contingency is included.
Currency changes labels only. No exchange conversion is applied
Related exercisePractise this calculation